Issues · tracker
5 open · 2 high priority · 1 blocked
| ID | Title | Priority | Due | Owner | Status |
|---|---|---|---|---|---|
| I-05 | Comms duct chainage 0+248 not on DBYD records Field discovery — needs mark-up + RFI |
High | 10 Jun | K. Hassan | New |
| I-04 | Subcontractor invoicing mismatch $4,200 |
Medium | 15 Jun | M. Cole | In progress |
| I-03 | Concrete pour Friday blocked · supplier delay |
High | 7 Jun | M. Cole | Blocked |
| I-02 | Site office Wi-Fi connectivity intermittent |
Low | — | D. Rangi | New |
| I-01 | Temporary fencing damaged by weather |
Medium | 8 Jun | D. Rangi | In progress |