MODULE MOCKUP · DESIGN · Drawing register · DQs · Design reviews · Coordination matrix · 7 templates
1 Drawing register 2 Package kanban 3 DQ thread 4 Coordination matrix Acceptance
Module Design Tender Construction ← Phases

Design module

Drawing register · design packages · DQs · review records · consultant coordination. Sits on top of the universal PM layer — same risks, issues, RFIs, just with a design lens.

6 new entities 7 templates 4–6 weeks build
Scene 1 of 4
Drawing register
All drawings across the project, with revision history. Filter by status (Concept · SD · DD · IFC · IFT · As-built). Click any row → detail with linked RFIs / NCRs.
AL
Adina Lieblich
Drawing register
47 drawings · 6 disciplines · 12 IFC · 8 IFT · 3 rev pending review
Number
Title
Rev
Status
Discipline · consultant
Issued
C-100
General Arrangement Plan1:500 · A1 · sheet 1 of 1
C
IFC
Civil · BG&E
12 Aug
C-101
Drainage Layout · Chainage 0+000 to 0+4001:200 · A1
D
IFC
Civil · BG&E
18 Aug
C-102
Drainage Layout · Chainage 0+400 to 0+8001:200 · A1
B
DD
Civil · BG&E
22 Aug
S-201
Headwall · Standard Detail1:50 · A3
B
IFT
Structural · Hyder
04 Sep
D-301
Manhole Type 1 (1800mm)1:20 · A3 · supersedes Type 2
C
SD
Drainage · BG&E
1 Sep
G-001
Geotech Investigation Plan1:500 · A1 · borehole locations
A
Concept
Geotech · GHD
14 Sep
Cross-references: drawing C-102 has 2 open RFIs · 1 active variation (CR-01) · 4 design queries. Click the drawing → see them all on the detail screen.
Scene 2 of 4
Design package kanban
Each package moves through Concept → SD → DD → IFC → IFT as it's developed. Cards show % complete and signoff status.
Design packages
5 packages · 1 IFC · 1 IFT · 2 DD · 1 SD · 1 concept · 2 late
Concept1
Foreshore reinstatement
S. Patel · BG&E2 weeks late
Schematic (SD)1
Outfall + headwall
Hyder5 Oct
Detailed (DD)2
Drainage 0+400–0+800
BG&E2 Sep
Manhole detail (Type 1)
BG&E3 DQs open
For construction1
Drainage 0+000–0+400
signed off 12 AugIFC
For tender1
Concrete works (slabs + headwall)
released 4 SepIFT
DDR template auto-fills

When you signoff a package (move to IFC), Lilach offers to auto-generate the Design Development Report for that stage. It pulls: package summary, all drawings in scope, open DQs, design assumptions, risk register impacts, signoff signatories. One click → branded PDF for client distribution.

Scene 3 of 4
Design Query · DQ-04 thread
DQs are RFI-shaped but internal to design. Threaded conversation between PM ↔ designer ↔ specialist. Auto-rolls into the DQ Log template.
DQ-04 · Manhole spec — capacity check
Raised 22 Sep by S. Patel · 4 messages · 1 attachment · related to drawing D-301
DESIGN QUERY · DQ-04 · OPEN

Does the 1500mm manhole pipe meet revised tidal capacity, or should we go to 1800mm?

S. Patel22 Sep · 09:14
Reviewing the tidal flood model from Cardno — at Q100 the manhole headloss is borderline against the 1500mm pipe. I think we need to step up to 1800mm. Need confirmation from hydrology and a cost estimate before I update the spec.

Related: drawing D-301 rev C, RFI-01 (still open).
M. Cole22 Sep · 14:32
From construction perspective: if we go 1800mm we'd need to also revise base slab thickness and bedding spec. Adds ~$11k to the line + a couple of days. Doable but earlier is better.
J. Patel · BG&E23 Sep · 11:08
Hydrology confirms 1500mm is undersized for revised Q100. Step up to 1800mm. I'll update D-301 to rev D and reissue. ETA Friday.

Will also need to update D-302 (junction at chainage 0+220) for consistency.
AL24 Sep · 08:42
Confirmed. Raising CR-02 (already drafted as variation $11k · 5 days). Will sign off when D-301 rev D is in. Closing this DQ when rev D lands.
Linked automatically: RFI-01 (manhole spec clarification) · Variation CR-02 (manhole 1800mm) · Drawing D-301 (will auto-link rev D when issued).
Scene 4 of 4
Consultant coordination matrix
Who's coordinated with whom. Auto-generated from drawings + DQs. Reads at a glance for sponsor meetings.
Consultant coordination · 5 disciplines × 4 consultants
Auto-generated from drawing register + DQ thread mentions · refresh on demand
Discipline ↓ · Consultant → BG&E (civil) Hyder (struct) GHD (geotech) Cardno (hyd)
Drainage layout
Manhole spec !
Headwall !
Foreshore reinstatement !
Geotech !
Coordinated
! Open DQ/RFI
Late / not started
Not applicable
Why this matters

Coordination gaps cause variations downstream. Spotting the red Foreshore reinstatement cell early lets you book a workshop now instead of a CR later. This single screen is the value-prop for the Design module — Mastt doesn't have it, Procore is contractor-focused, InEight needs a 6-month rollout. We ship it in 4 weeks.

Acceptance
Design module · shippable when
Tick as Adina QAs the live build. Persisted to localStorage per phase.
Design module acceptance · 0 of 24