Weekly status · period 23

Weekly status report

A one-page exec summary the sponsor reads in 90 seconds and a delivery team reads in 5 minutes.
FDU-S2-2026 WSR · 2026-W23
Project
Foreshore Drainage Upgrade · Stage 2
PM
A. Lieblich
Sponsor
Director, Engineering
Period
8–12 Jun 2026
Phase
Construction · 38%
Overall
Schedule Amber · 4 days behind on culvert install due to ground conditions; recovery plan in place. ↓ from G
Budget Green · 96% to forecast, $58k contingency remaining. → stable
Scope Green · no scope changes this period. → stable
Quality / safety Green · 0 LTI · 1 near-miss reported and closed · 14 daily inspections passed. → stable
38%
Complete
−4d
Schedule variance
$58k
Contingency left
7
Open risks
3
Open issues
Achieved this week

Done.

  • Culvert C-04 install complete · concrete pour cured · headwall ready for week 24.
  • Survey QA of chainages 0+000 to 0+220 signed off by site engineer.
  • Stakeholder briefing to local business association completed — see meeting minutes.
  • Procurement of revised geotextile (Risk R-09 mitigation) confirmed for delivery 17 Jun.
Planned next week

Next five days.

  • Start culvert C-05 install (subject to soils confirmation Mon AM).
  • Headwall pour C-04 — concrete strike Wed.
  • Internal cost-to-complete review (Fri AM, attendees: PM, QS, eng).
  • Submit RFI-018 (revised flow rate assumption — see risks).
Top risks & issues this period
IDDescriptionP × IOwnerStatus
R-09Geotech variation could require revised pipe bedding spec on chainage 0+220 to 0+340.3×4 = 12K. HassanActive
R-11Stage 2 procurement schedule risk if Stage 1 hold-points slip into Stage 2 window.3×3 = 9A. LieblichMonitor
I-06RFI-016 still open with consultant after 14 days; chasing.A. LieblichOpen
I-07Site access constraint Wed AM due to community event.Site engResolved
Ask of sponsor

Decision required by Wed 11 Jun: approval to proceed with revised geotextile spec (Risk R-09 mitigation) at additional cost of $11,400 ex GST, drawn from contingency. Refer Change Request CR-04 attached.