Site diary · day 64

Site diary

Daily site record. Conditions, crew, work done, issues, decisions, photos.
FDU-S2 · SD-064 2026-06-11 · Wed
Project
Foreshore Drainage Upgrade · Stage 2
Site engineer
K. Hassan
Foreman
D. Rangi
Chainage worked
0+220 to 0+260
Hours on site
07:00 — 16:30
Conditions
☀️
Sky
Clear
🌡️
Max temp
21°C
🌬️
Wind
12 km/h SW
💧
Rainfall
0 mm
🌍
Ground
Dry
Crew & equipment on site

Personnel

Site engineer1PPE OK
Foreman1PPE OK
Pipelayers3PPE OK
Excavator operator (subcontractor · A&K Civil)1PPE OK
Traffic controllers2PPE OK

Plant & equipment

20T excavator (Cat 320)1Pre-start ✓
Tipper truck (8m³)2Pre-start ✓
Compactor (vibratory)1Pre-start ✓
Work completed today

Done · chainage 0+220 to 0+260

  • Excavated trench chainage 0+220 to 0+260 to design level RL 12.4 (40 lin.m).
  • Imported and compacted bedding (Type 1, 150mm thickness) — density test sample taken (T-064-A).
  • Laid 600mm RCP pipes, 8 lengths × 2.4m, joints sealed and inspected by SE.
  • Backfilled to 300mm cover with select fill, compacted to 95% MDD (T-064-B taken).
  • Removed approx 14m³ unsuitable spoil to authorised tip (ticket #A0418-A0420).
Issues, instructions, visitors
Issue · noted

10:40 — Found existing 50mm comms duct at chainage 0+248 not shown on dial-before-you-dig records. Work paused 25 min. Telco contacted (ref TLC-2026-3318). Confirmed in-service. Diverted comms duct above pipe, hand-excavated around it. Notified consulting engineer (verbal). To be drawn on as-built. Photos #003–#006 taken.

Visitor / inspection

13:30 — J. Park (Engineer of Record) attended for routine inspection of pipe bedding and joint sealing. Walked chainage 0+220 to 0+260. No defects raised. Verbal approval to backfill. Inspection report INSP-022 logged.

Verbal instruction

14:15 — J. Park: pause RCP laying past chainage 0+340 until RFI-018 (flow rate assumption) resolved. Acknowledged. Crew to focus on chainages 0+260 to 0+340 from Thu.

Photos taken
001
trench
0+220 AM
002
bedding
003
comms duct
004
comms duct
005
diversion
006
diversion
007
pipe joint
008
backfill PM
Planned tomorrow

Continue trenching chainage 0+260 to 0+300. Bedding + RCP. Survey QA for chainages 0+220 to 0+260 (today's work) before any further backfill. Receive geotextile delivery (revised spec, ref Risk R-09). Toolbox topic: comms duct handling.

Diary by
K. Hassan
Site Engineer
Reviewed by
A. Lieblich
Project Manager