PMBOK · the integrating document

Project Management Plan

How this project will be planned, executed, monitored, and closed. The single source of truth.
FDU-S2 · PMP-v2 Rev 2 · 2026-04-01
Project
Foreshore Drainage Upgrade · Stage 2
PM
A. Lieblich
Sponsor
Director, Engineering · City Council
Approved budget
$1,820,000 ex GST
Programme
Apr 2026 → Mar 2027
1 · Scope

Eight hundred metres of new stormwater main.

This project delivers ~820 lin.m of new 600mm RCP stormwater main along Foreshore Parade between Beach Road and Marina Drive, replacing the existing 1970s-era 375mm pipe network which has reached end-of-life capacity. Includes five new manholes (MH-08 to MH-12), two new outfall headwalls (H-04 and H-05), reinstatement of kerb, channel, footpath, and landscape, and a temporary diversion of pedestrian traffic during construction.

Stage 1 (chainage 0+000 to 0+220) completed Feb 2026. This plan covers Stage 2 (chainage 0+220 to 0+820). Stage 3 (chainage 0+820 to 0+940 — outfall and rock armouring) is a separate project under PMP-S3.

2 · Objectives & success criteria

What "done" means.

#ObjectiveSuccess criterion (measurable)
O1Increase stormwater capacity through foreshore corridorDrainage system passes 1:100yr ARI design flow with 300mm freeboard.
O2Reduce nuisance flooding at low-point on Marina DriveZero overtopping events during 12-month defect liability period.
O3Replace failing asbestos-cement pipes100% of in-scope AC pipe removed, disposed under licensed regime, certificate of disposal retained.
O4Maintain pedestrian and trader accessForeshore Parade pedestrian access open daily 07:00–17:00. No more than 4 weeks of single-business-frontage closure.
O5Deliver within budgetFinal cost within +/− 3% of approved $1.82m (acceptable range $1.766m to $1.875m).
O6Zero lost-time injury0 LTIs over the 12-month construction window.
3 · Key deliverables

Physical and documentary.

DeliverableOwnerTarget dateStatus
~820 lin.m new 600mm RCP stormwater mainContractorFeb 2027In progress
5 × new manholes (MH-08 to MH-12)ContractorJan 2027In progress
2 × outfall headwalls (H-04, H-05)ContractorDec 2026In progress
Reinstatement (kerb, channel, footpath, landscape)ContractorMar 2027Not started
Traffic management plan + community engagementPM + CommsOngoingIn progress
As-built drawingsSurveyor + EORMar 2027Not started
Asset handover pack to operations teamPMMar 2027Not started
Project closure report + lessons learnedPMApr 2027Not started
4 · Phases & milestones

Five phases.

01
Mobilisation & site establishment
Hoarding, traffic management plan live, crew inducted
Apr 2026
→ Apr 2026
4 wks
02
Earthworks & pipe install — chainages 0+220 to 0+500
First half of mainline installed and inspected
May 2026
→ Aug 2026
16 wks
03
Earthworks & pipe install — chainages 0+500 to 0+820
Second half of mainline + structures
Aug 2026
→ Dec 2026
16 wks
04
Reinstatement
Kerb, channel, footpath, landscape, line marking
Dec 2026
→ Feb 2027
10 wks
05
Practical completion & closure
As-builts · handover pack · sign-off · lessons learned
Feb 2027
→ Apr 2027
6 wks
5 · Governance & authority

Who can say yes.

DecisionAuthorityCadence
Scope changes (no cost / time impact)PM (notify EOR & Sponsor)As required
Change requests < $20kPM (notify Sponsor)As required
Change requests $20k – $100kSponsor (recommend by PM)Within 7 days
Change requests > $100kCouncil delegation (recommend by Sponsor)Within 21 days
Pause work for safetySite engineer, foreman, EOR, PM (anyone)Immediate
Final practical completion sign-offSponsor + EOR (joint)End of phase 5

Full responsibility split: see RACI matrix (FDU-S2 · RACI-v2).

6 · Assumptions & constraints

What we're betting on.

TypeStatementLinked risk
AssumptionWet weather lost days do not exceed 18 across construction window.R-01
AssumptionExisting utility records (DBYD + council asset register) are substantially accurate.R-03
AssumptionStage 1 completion handover is final — no rework recalled to this contract.R-11
AssumptionAboriginal heritage clearance obtained for full alignment (granted 2 Jun 2026).R-07
ConstraintNo weekend works permitted (council noise bylaw).
ConstraintPedestrian access along Foreshore Parade must remain open 07:00–17:00 daily.R-06
ConstraintCouncil elections Oct 2026 — non-essential decisions paused 4 weeks before.R-17
ConstraintApproved budget $1,820,000 — variance >3% requires Sponsor + delegated authority approval.
7 · Exclusions

Not in scope.

  • Stage 3 (outfall + rock armouring) — separate project under PMP-S3.
  • Foreshore Parade carriageway repaving beyond the trench footprint + 500mm overlap.
  • Adjacent property landscape restoration beyond council road reserve.
  • New street lighting and CCTV (separate council programme).
  • Power utility undergrounding (handled by utility owner).
8 · Referenced documents
RefDocumentVersion
RACI MatrixFDU-S2 · RACI-v2
Stakeholder RegisterFDU-S2 · SR-v3
Risk RegisterFDU-S2 · RR-v8
Issue TrackerFDU-S2 · IT-v23
Budget TrackerFDU-S2 · BT-M03
Inspection & Test PlanITP-S2 · Rev 1
Design drawings (Issued for Construction)C-201 Rev B · C-203 Rev A
Stage 1 closure reportFDU-S1 · CR-final
Prepared & recommended by
A. Lieblich
Project Manager · Contractor
Approved by
Director, Engineering
Sponsor · City Council